ADDRESS: Bringelly NSW 2556
DURATION: 9 Days
- Supply and install 161m2 shed to post construction including:
- Supply and install all new posts, jump up brackets, pitching beams, rafters and
battens where required
- Supply and install corrugated roofing over
- Supply and install all new treated pine joints and associated decking
- Supply and install 1x2-treat step at 900mm wide only
- Supply and install 262m2 shed to post construction including:
- Supply and install all posts, jump up brackets, pitching beams, rafters and
battens where required
- Supply and install corrugated roofing over
- Supply and install all new treated pine joints and associated decking
- Supply and install 1x 2-treat step @ 900mm wide only
- Supply and install 1x free-standing awning at 210m2 only
- Supply and install all posts, pitching beams, rafter’s ad battens where required
- Supply and install corrugated roofing over